Sask. city borrowing millions to cover missing donor cash for massive new arena
![Prince Albert arena and recreation centre The new Aquatic and Arenas Recreation Centre - View of the wave pool and water slides area. (Source: City of Prince Albert)](/content/dam/ctvnews/en/images/2024/2/18/prince-albert-arena-and-recreation-centre-1-6774130-1708300005252.png)
Saskatchewan’s third-largest city plans to borrow an additional $18 million to cover funding gaps for a major arena and aquatic centre.
Prince Albert’s city council approved the loan on Monday, adding to the $46 million in debt already incurred on the project, which has faced cost overruns.
The city said this new loan wasn’t due to an increase in the project budget.
In a statement released before the meeting, city manager Sherry Person said administration failed to consider that fundraising commitments would be paid over several years, rather than in a lump sum.
Mayor Greg Dionne told councillors he’s confident the $18 million loan would be covered by donation money already committed to the project, but not yet paid.
“These are business leaders or community leaders that are stepping forward and going to donate to us millions of dollars towards this project,” he said.
“But they've asked us, ‘We're gonna give you a million dollars, but can we pay you over the next five years?”
Dionne said these pre-existing commitments are the reason the new loan has a five-year repayment schedule, rather to the 30-year timeline on the $46 million in debt.
In January, the city said the project was over halfway complete. The new aquatic centre and arenas will house two NHL-sized rinks with seating for nearly 800 people. The 51,500 square-foot aquatics area will feature a 9-lane competitive pool, a wave pool, lazy river, whirlpool and two water slides.
The city expects the recreation centre to act as the cornerstone of a new commercial district, with plans already in place for an event centre at the site and a new hotel already built.
Councillor Terra Lennox-Zepp was the main opponent of the motion on Monday evening.
She pointed out the city was paying $1.8 million per year in interest on the $46 million in debt already incurred for the project.
“That's not a piece of lumber in the ground. That's not an hour of labor. That's just the interest we're currently paying for that for one year only. It would be financially irresponsible of us as a city to incur a further $18 million loan on this project,” she said.
“It would absolutely be financially irresponsible of us to incur more millions onto this, this debt, and we have no capacity to pay for it.”
Lennox-Zepp also expressed concern over a $700,000 contract to a company to secure sponsors for the massive facility, and a $4 million commitment for architecture work for the as-yet unfunded 4,500-seat event centre.
“That's just the architectural work. And we have absolutely no financial capacity, no plan to pay for and to build that 4,500 seat event center. So a major concern here.”
She advised council to put the project on hold until the city was in a better position to pay for it.
Ward 5 councillor Dennis Ogrodnick said it would be “totally irresponsible” to stop the project now.
“You can’t stop a project; it’s a year away from opening and you want to stop and give up on it? No. This is the responsible thing to do — we need to follow through on this,” he said.
(Source: City of Prince Albert)
Councillor Blake Edwards scoffed at the idea of pausing the project.
“We’ve got buildings being built in progress, but let’s halt it and let the work sit still? … That’s the most ridiculous thing I’ve ever heard.”
He said many Prince Albert families are driving an hour to Melfort to use that community’s wave pool because the city doesn’t have comparable facilities.
Tony Head supported the motion to borrow the money, but he did express concerns that city administration had earlier told council it expected $20 million from donors this year, and only recently revealed it would just receive $6 million of that in 2024.
“That’s a huge oversight in my opinion,” he said.
“I’m just going by what the report had said. So there was some misreporting from possibly the company, possibly administration … because that’s not what we were told.”
The motion carried. It will bring the city’s total debt to $115.6 million, just $4.4 million short of its borrowing limit.
In 2022, the city applied to the provincial municipal board to raise its debt limit to $120 million up from $75 million due to the rising costs of the project.
CTVNews.ca Top Stories
![](https://www.ctvnews.ca/polopoly_fs/1.6778341.1708561001!/httpImage/image.jpg_gen/derivatives/landscape_800/image.jpg)
'I got no remorse': Greg Fertuck, convicted of murdering missing spouse, sentenced to life in prison
Greg Fertuck will spend life behind bars with no chance of parole until he is 90 years old, a judge ruled on Thursday at Saskatoon's Court of King's Bench.
'Ford's dry summer begins': All LCBO stores closed as workers go on strike
All LCBO stores are closed on Friday as thousands of workers hit the picket lines after their union and employer failed to reach an agreement.
Britain's Labour on track for landslide victory, exit poll suggests, amid anger with Conservatives
Britain's Labour Party headed for a landslide victory Friday in a parliamentary election, an exit poll suggested, as voters punished the governing Conservatives after 14 years of economic and political upheaval.
Saskatchewan has the lowest hourly minimum wage. How does it stack up to the rest of Canada?
Hourly minimum wages increased in several Canadian provinces this spring with more on the horizon, which economists say will likely impact workers and businesses differently.
Trying to sell or buy a home this summer? What a realtor says you should know
In the first few weeks of summer, the real estate sector is experiencing an upturn marked by more housing inventory, a Canadian realtor says
No Frills grocery stores drop 'multi-buy' offer
As receipts tick ever higher for Canadians at the grocery store and shoppers continue to search for savings, one Canadian grocer has ended a perceived deal.
Hurricane Beryl churns toward Mexico after leaving destruction in Jamaica and eastern Caribbean
After leaving a trail of destruction across the eastern Caribbean and at least nine people dead, Hurricane Beryl weakened as it chugged over open water toward Mexico's Yucatan Peninsula on Thursday, going from the earliest Category 5 hurricane in the Atlantic to Category 2 by the afternoon.
CSIS director David Vigneault stepping down after seven years on the job
David Vigneault says he is stepping down from his job at the head of Canada’s spy agency. The director of the Canadian Security Intelligence Service, who spent seven years at the helm, is leaving the public service altogether.
Biden tells Democratic governors he needs more sleep and plans to stop scheduling events after 8 p.m.
U.S. President Joe Biden told Democratic governors during a meeting at the White House on Wednesday that part of his plan going forward is to stop scheduling events after 8 p.m. so that he can get more sleep, according to three sources briefed on his comments.